PERHITUNGAN KEBUTUHAN KAPASITOR DAYA (CAPACITOR BANK) PADA SISTEM KELISTRIKAN GEDUNG RSG-GAS

Teguh Sulistyo, TS and Kiswanto, Kiswanto and Yuyut Suraniyanto, YS and Taufiq, Muhammad (2007) PERHITUNGAN KEBUTUHAN KAPASITOR DAYA (CAPACITOR BANK) PADA SISTEM KELISTRIKAN GEDUNG RSG-GAS. Buletin "Reaktor". ISSN ISSN: 0216-2695

[thumbnail of Teguh S_ok.pdf]
Preview
Text
Teguh S_ok.pdf

Download (300kB) | Preview

Abstract

PERHITUNGAN KEBUTUHAN KAPASITOR DAYA (CAPACITOR BANK) PADA SISTEM KELISTRIKAN GEDUNG RSG-GAS. Dalam rangka menjaga agar nilai faktor daya tidak turun dan tetap berada di atas nilai yang disyaratkan oleh PLN yaitu > 0,85 serta melaksanakan program penghematan pemakaian energi listrik khususnya pada gedung RSG-GAS maka salah satu upaya yang dapat dilakukan adalah melalui pemasangan kapasitor daya (capasitor bank) yang ditempatkan pada masing-masing jalur (train) sistem kelistrikan gedung RSG-GAS sesuai dengan kebutuhan. Berdasarkan hasil perhitungan dengan menggunakan data kwitansi dari rekening pemakaian listrik PRSG pada tahun 2006, kebutuhan kapasitor daya untuk sistem kelistrikan gedung RSG-GAS pada masing-masing train sebesar 400 kVAr, dan faktor daya (cos φ) dapat dinaikkan dari 0,75 menjadi 0,95. Dengan adanya kenaikkan faktor daya ini maka biaya rekening pemakaian kVArh gedung PRSG dapat kurangi.

Kata kunci : kapasitor daya.

ABSTRACT

CALCULATION OF REQUIREMENT OF CAPACITOR ENERGY (CAPACITOR BANK) ELEKTRICAL SYSTEM AT RSG-GAS BUILDING. In order to taking care of power factor value do not go down and reside in of required value that is > 0,85 and also execute program thrift of usage of electrics energy specially at building of RSG-GAS hence one of the effort able to be by is to installation of energy capacitor (capacitor bank) placed at each band (system train) electrical system of building of RSG-GAS as according to requirement. Pursuant to result of calculation by using receipt data of account usage of electrics of PRSG in the year 2006, requirement of energy capacitor for the system of electrical of building of RSG-GAS at each train equal to 400 kVAr, and power factor (Cos φ) can be boosted up from 0,75 becoming 0,95. With existence of raising of this power factor hence expense of account usage of building kVArh of PRSG can lessen.

Key words : capasitor bank

Item Type: Article
Subjects: Taksonomi BATAN > Reaktor Nuklir > Teknologi Reaktor > Sistem Reaktor
Taksonomi BATAN > Reaktor Nuklir > Teknologi Reaktor > Sistem Reaktor
Divisions: BATAN > Pusat Reaktor Serba Guna
IPTEK > BATAN > Pusat Reaktor Serba Guna
Depositing User: Administrator Repository
Date Deposited: 31 Jan 2019 08:24
Last Modified: 31 May 2022 03:38
URI: https://karya.brin.go.id/id/eprint/8527

Actions (login required)

View Item
View Item