MODIFIKASI PRE-HEATER MENJADI PRE-COOLER PADA UNTAI UJI BETA. Fasilitas
FASSIP-01 mempunyai komponen pre-heater dengan ukuran panjang 800 mm dengan
diameter 10 inchi yang mempunyai kapasitas 50 kW dengan 10 batang pemanas preheater
digunakan pada FASSIP-01 untuk memanaskan sistem aliran, dengan adanya
perkembangan penelitian maka fasilitas BETA sudah tidak dioperasikan lagi, sedangkan
dengan adanya fasilitas untai FASSIP-01 baru untai tersebut memerlukan sistem pendingin,
dan untuk memanfaatkan pre-heater pada FASSIP-01 maka pre-heater dimodifikasi
menjadi pre-cooler dengan sistem pendingin spiral yang dihubungkan dengan sistem Heat
Sink System (HSS) pada untai FASSIP-01. Sehingga perlu dilakukan penelitian untuk
mengetahui karakteristik pendingin secara pasif. Maka pada tahun 2015 dibuat Untai
FASSIP-01untuk mempelajari karakteristik pendingin secara pasif. Kegiatan yang dilakukan
pada tahun 2016 adalah memodifikasi pre-cooler dari sistem kontak tak langsung menjadi
kontak langsung dan mengoperasikan Untai FASSIP-01dengan tujuan untuk memperoleh
data pengukuran temperatur, daya listrik, frekuensi dan laju alir fluida yang diperlukan untuk
mendukung penelitian sistem keselamatan pasif. Modifikasi pre-cooler dari kontak tak
langsung menjadi kontak langsung telah berhasil menurunkan temperatur yang semula 24⁰C
menjadi dibawah 10⁰C sesuai dengan yang diinginkan.
Kata kunci : Modifikasi, pre-heater, pre cooler, sirkulasi alam, pendinginan.
ABSTRACT
MODIFY PRE-HEATER BEING PRE-COOLER ON BETA TEST STRANDS. The BETA test
strand facility has a pre-heater component with a length of 800 mm in diameter of 10 inches
having a capacity of 50 kW with 10 preheater heating rods used on the BETA test strand to
heat the flow system, with the development of the BETA facility no longer operated, While
the new FASSIP-01 strand facility requires a cooling system, and to utilize the pre-heater on
the BETA test strand the pre-heater is modified to a pre-cooler with a spiral cooling system
connected to the Heat Sink System (HSS) system on the strand FASSIP-01. So it is
necessary to do research to know the coolant characteristic passively. Then in 2015 made
FASSIP-01strand to study the characteristics of the coolant passively. The activities carried
out in 2016 are to modify the pre-cooler of the indirect contact system into direct contact and
operate the FASSIP-01strand with the aim of obtaining data on the temperature, power,
frequency and fluid flow rate required to support the passive safety system research. The
modification of the pre-cooler from indirect contact into direct contact has succeeded in
lowering the original temperature of 24⁰C to below 10⁰C as desired.
Keywords: Modification, pre-heater, pre cooler, natural circulation, cooling.
Item Type: | Article |
---|---|
Subjects: | Taksonomi BATAN > Keselamatan dan Keamanan Nuklir Taksonomi BATAN > Keselamatan dan Keamanan Nuklir |
Divisions: | BATAN > Pusat Teknologi dan Keselamatan Reaktor Nuklir IPTEK > BATAN > Pusat Teknologi dan Keselamatan Reaktor Nuklir |